Thursday, November 18, 2004

Thursday November 18, 2004:

We now have the first coat of paint around the entire house. We have also tightened up the porch handrails and posts.

This is were our new ADA access will be. Along the side of the house will be our staging area.

Soon we will start cleaning up the back house and making it usable space.

Friday, November 12, 2004

Friday November 12, 2004:

This week we finished the deconstruction of theback lean-to. We also moved all the bushes away from the house and pulled all of the old stumps from the lawn. The paint strippers and the new painters have been making good progress and they should finish early next week.

Friday, November 05, 2004

Friday November 5

This week I started the demolition of the back lean-to. The first room is off as well as the roof. I am saving all usable wood from the original structure for later use.
The paint stripers have been burning of the paint and preparing for the first coat of paint.