The student intern work day went well. We picked up the outside of the building and started some inside cleaning too. A big thanks to the student interns and Tom.






June 21, 2005
All the ruff in plumbing is done. After all the interior finish work is finished we will finish the final steps of the plumbing work by installing the fixtures.
Friday, June 17, 2005
Friday, June 10, 2005
June 10, 2005
Today we finished all the downstairs framing. Next week we will finish the upstairs closets, then we will have the electrical, plumbing and hvac installed.
Thursday, June 09, 2005
June 9, 2005
We now have the walls framed in, and can start on the details of the counters and the closets.
Wednesday, June 08, 2005
Tuesday, June 07, 2005
June 7, 2005
Building new walls and extending the floor joists will keep the new office area structurally sound.